WHEN AN ARBITRATION CLAUSE MAY NOT LET YOU ARBITRATE

In Far Ocean Sea Products Pte Ltd v United Overseas Insurance Limited [2026] SGHC 182, the Singapore High Court held that an arbitration clause applying to disputes over the amount payable became operative only after the insurer had admitted all aspects of liability.

The fire, the claim and the time bar. Far Ocean Sea Products Pte Ltd (“Far Ocean”) operated premises with processing and cold rooms for its frozen seafood business, and its fire policy with United Overseas Insurance Limited (“UOI”) insured the premises for one year for up to S$12.58 million (Judgment [4]–[5]).

The Policy contained a 12-month contractual time bar as set out below (Judgment [5(a)]):

“In no case whatever shall [UOI] be liable for any loss or damage after the expiration of twelve (12) months from the happening of the loss or damage unless the claim is the subject of pending action or arbitration.”

And the arbitration clause in the Policy is set out below (Judgment [5(b)]):

“If any difference shall arise as to the amount to be paid under this Policy (liability being otherwise admitted) such difference shall be referred to an arbitrator to be appointed in accordance with the statutory provisions in that behalf for the time being in force.

Where any difference is by this Condition to be referred to arbitration the making of an award shall be a condition precedent to any right of action against [UOI].

Unless any such action or suit be commenced within six (6) months of the making of an award [UOI] shall not be liable to make any payment in excess of the amount of the award.”

A fire caused by an electrical fault severely damaged the premises on 28 June 2024, including the electrical systems serving the cold rooms, and significantly disrupted Far Ocean’s operations. The contractual time bar would therefore expire on 28 June 2025 (Judgment [6]–[7]).

The parties nevertheless continued discussing the claim for months after that date: by May 2025, UOI had allowed Far Ocean to commence works for only two of seven claimed items while disputing coverage for the cold rooms and temporary works. However, UOI only formally relied on the time bar in December 2025 (Judgment [9]–[11]).

Far Ocean then commenced arbitration and applied under section 10(1) of the Arbitration Act 2001 for the Court to extend the contractual time for pursuing the arbitration (Judgment [11]).

The key question: what does “liability being otherwise admitted” mean? The Court first had to determine whether Far Ocean’s proposed dispute fell within the arbitration clause, a threshold issue because the Court’s statutory power to extend time arose only for a dispute to which the arbitration agreement applied (Judgment [28], [34]).

The key phrase therefore was “liability being otherwise admitted” (Judgment [40]): was it sufficient that the insurer, UOI, had admitted to some liability, such that the insured Far Ocean can refer both questions of liability and quantum to arbitration, or must liability be wholly admitted such that only questions of quantum remain?

The Court accepted UOI’s interpretation that the words “liability being otherwise admitted” required all questions or aspects of liability to have been admitted, leaving only the amount payable for the arbitrator to determine (Judgment [43]).

The Court gave three principal reasons which are summarized in Judgment [78]:

  1. The interpretation reflected the wording, because a different result would require “liability” to be qualified by a word such as “some” or “partial”.

  2. It fitted a reasonable commercial purpose of allocating legal liability questions to judges and technical quantum questions to an arbitrator with relevant valuation, claims-adjustment or accounting expertise.

  3. It was consistent with decades of English decisions interpreting materially identical insurance clauses (Judgment [78]).

In doing so, the Court made clear that the generally pro-arbitration stance adopted by Singapore does not change the result, as presumptions favouring arbitration must give way to the parties’ objectively expressed words where those words limit arbitration to a particular subset of disputes (Judgment [49]–[51]).

Why the arbitration could not proceed. Because at least two liability issues remained unresolved — whether the cold rooms fell within the Policy and whether Far Ocean could convert its reinstatement claim into a loss-of-value claim after selling the premises — liability had not been “otherwise admitted”, and the arbitration agreement had not become operative (Judgment [79]–[80]).

Accordingly, the Court held that it had no power to extend time under section 10(1) and dismissed Far Ocean’s application, observing that an insured could file a protective court claim within the contractual time bar if the insurer was taking time to decide liability (Judgment [81]–[84]).

What contractors should take note of. An arbitration clause sometimes is glossed over when parties review an agreement. This decision is a reminder that not all arbitration clauses are the same.

Arbitration clauses may differ in terms of not just the arbitral institutes and rules, but may also differ in that some arbitration clauses (as in this case) would have to be read with specific time bar clauses, while other arbitration clauses may require parties to engage in tiered dispute resolution mechanisms. Yet other arbitration clauses may restrict the types of disputes that can be brought to arbitration. 

So, pay attention to your dispute resolution clauses.

This publication is not intended to be, nor should it be taken as, legal advice; it is not a substitute for specific legal advice for specific circumstances. You should not take, nor refrain from taking, actions based on this publication. Chancery Law Corporation is not responsible for, and does not accept any responsibility for, any loss or damage that may arise from any reliance based on this publication.

Xian Ying Tan