Singapore's New Digital Infrastructure Bill
The Ministry of Digital Development and Information (“MDDI”) introduced the Digital Infrastructure Bill (the “Bill”) for First Reading in Parliament on 8 September 2026. The Bill was passed on 7 October 2026.
It will come into operation on a date appointed by the Minister by Gazette notification (s 1).
The Bill licenses providers of major foundational digital infrastructure (FDI) services and operators of data centres (ss 7(1), 23(1)). The Info-communications Media Development Authority ("IMDA") administers it (ss 2, 4(1)).
Part 3 of the Bill is directed at the security and resilience of major FDI services (s 15). Part 4 of the Bill is directed at the environmental sustainability of data centres (s 35).
The two licences are independent of each other. An operator that provides a data centre facility service from a data centre with a critical IT load of at least 10 MW needs both (ss 7(1), 23(1); Schedule, para 3).
Major FDI Licence: Security and Resilience
Scope. The major FDI licence will apply to providers of the following services (Schedule, paras 2 and 3):
· a data centre facility service delivered in a data centre with a critical IT load of at least 10 MW; and
· an Infrastructure-as-a-Service (IaaS) or Platform-as-a-Service (PaaS) cloud service that has generated revenue from users in Singapore of at least $100 million a year on average over the 3 preceding years.
For now, it does not apply to Software-as-a-Service (SaaS) or to data centres used solely for the operator's own internal purposes (s 2, "data centre facility service"; Schedule, para 3).
Extraterritorial reach. This regime catches services provided from within or outside Singapore to users in Singapore, and services provided wholly or partly from Singapore to users anywhere (s 3(1)). A licensee located outside Singapore must appoint a person in Singapore to accept service (s 10(4)).
This licence is concerned with security and resilience. The licensee must implement prescribed security measures, measures to minimise unexpected interruptions, and business continuity and disaster recovery plans, and must notify IMDA of prescribed cybersecurity incidents and service disruptions (s 15).
Codes and directions. Licensees must comply with applicable codes of practice (s 16(8)), which must not be inconsistent with codes of practice or standards of performance under the Cybersecurity Act 2018 (s 16(3)). IMDA may issue directions, including for audits and remediation (s 17(1)-(2)). It may also direct a licensee to notify affected Singapore users of protective measures after a cybersecurity threat or incident (s 17(3)).
Emergency powers. The Minister may, by certificate, direct any person to take measures against a serious and imminent threat to national security, the economy or similar interests arising from a threat to a major FDI service (s 18(1)).
Data Centre Licence: Environmental Sustainability
Scope. The data centre licence will apply to operators of:
· a data centre carrying a critical IT load of 3 MW or more (ss 2, 23(1)).
A person operates a data centre if it controls the operating, maintenance or environmental policies, whether the facility serves customers or the person's own use (s 23(2)(a)).
So internal-use facilities of 3 MW or more fall within Part 4 even though they fall outside Part 3 (s 2, "data centre facility service"; s 23(2)(a)).
Exclusions. Part 4 does not apply to Government and public authority data centres, educational institutions' research facilities, or telecoms, electricity and gas licensees' data centres dedicated to their licensed activities (s 3(5)).
This licence is concerned with environmental sustainability. The licensee must meet prescribed energy and water efficiency requirements (s 35) and submit a compliance report to IMDA annually (s 36(1)).
In deciding whether to grant or renew a data centre licence, IMDA must consider the applicant's experience, the facility's energy and water efficiency, and the public interest (s 25(2)). It may also weigh the energy sources used, carbon mitigation, imported electricity, Singapore's emissions commitments, and economic or strategic value (s 25(3)). On the last factor it must have regard to the opinion of the Economic Development Board (s 25(4)).
Enforceable commitments. Licence conditions may require the licensee to:
· perform economic or strategic undertakings made in its application (s 27(3)(c));
· establish and fund a low-carbon energy project in Singapore (s 27(3)(d));
· capture emissions or surrender eligible international carbon credits (s 27(3)(e));
· use imported electricity (s 27(3)(f)); or
· cap its use of electricity from a specified energy source (s 27(3)(g)).
Commitments made to secure capacity in an allocation exercise (s 24(4)) can therefore be enforced as licence conditions (s 27(3)(c)).
Change of control. A licensee must inform IMDA within 7 days of becoming aware that a person has become or ceased to be a 5% controller, has become an indirect controller, or has acquired its data centre business as a going concern (s 33). This is a notification duty. Prior written approval is required only for a transfer of the licence itself, failing which the transfer is void (s 28(1)-(2)).
This change-of-control reporting duty (Part 4, Division 2) applies only to data centre licensees; Part 3 has no equivalent, though major FDI licences are likewise non-transferable without approval (s 12).
Sanctions
Financial penalties. Under both regimes, IMDA may impose a penalty of up to the higher of $1 million or 10% of annual Singapore turnover (ss 20(2), 40(2)). Failing to comply with a direction carries up to $100,000 (ss 20(3), 40(3)). At least 21 days' notice and an opportunity to make representations are required (ss 21, 41).
Licence action. IMDA may revoke a licence or suspend it for up to one year (ss 19(1), 39(1)). For a data centre licence it may also reduce the permitted critical IT load (s 39(2)(b)).
Energy-cap breaches. Where a licensee breaches a s 27(3)(g) condition, IMDA may order it to transfer carbon credits to offset the extra emissions and to pay over its cost savings (s 39(3)).
Individuals. Officers who consent to, connive in, or fail to take reasonable steps to prevent a corporate offence are liable for the same offence (s 54(2)).
Practical takeaways
· Check both thresholds. A 10 MW co-location or cloud facility needs two licences; a 3 MW enterprise facility needs only a data centre licence (ss 2, 7(1), 23(1), 23(2)(a); Schedule, para 3).
· Much is still to come. The operative security, resilience and efficiency standards are all "as may be prescribed" (ss 15, 35). As a first step, data centres will have to meet facility-level energy efficiency requirements, including Power Usage Effectiveness (PUE) requirements, which will apply to existing and new data centres (see MDDI press release: https://www.mddi.gov.sg/newsroom/new-digital-infrastructure-bill-to-strengthen-the-foundations-for-singapore-s-digital-economy/).
· Application promises become binding. Undertakings made to win capacity can be written into the licence and enforced through the penalty regime (ss 27(3)(c), 40(1)(d)).
· Deal documents. A change in shareholding or control of a data centre licensee triggers 7-day reporting, not prior approval (s 33). Prior written approval is required only for a transfer of the licence itself (ss 12(1), 28(1)).
· Customer contracts. Operators answer for the efficiency of customer-installed IT equipment (s 35(b)), so co-location agreements will need flow-down terms.
This publication is not intended to be, nor should it be taken as, legal advice; it is not a substitute for specific legal advice for specific circumstances. You should not take, nor refrain from taking, actions based on this publication. Chancery Law Corporation is not responsible for, and does not accept any responsibility for, any loss or damage that may arise from any reliance based on this publication.